Investigation on Causes of Delays and Cost Overruns of Construction Projects in Afghanistan

Irshad Habibi, Chandigarh University

Citation Information: Habibi, I. (2023). Investigation on causes of delays and cost overruns of construction projects in afghanistan. Journal of Management Information and Decision Sciences, 26 (4),1-16.

Abstract

The research indicates a big role of delay and cost overrun during the execution of construction projects in Afghanistan. However, in Afghanistan, due to a number of hurdles, a majority of construction projects are not completed in the required time, unfortunately. This research paper illustrates the investigation of the reasons why cost overruns delay construction projects. Problems were investigated via questionnaires, interviews physically with the person, On-site interviews with officials of the survey planned focusing on the main factors which could affect the budget delay in time overruns. A Questionnaire survey was filled with around 91 responders and found the three most perilous factors of Time Overrun are: (1) Challenge of security during the implementation of projects, (2) Corruption, (3) Difficulties in the financing of the project by the contractor, furthermore, find three most critical factors of Cost Overruns are: (1) Meager site management and administration, (2) Accidents during construction, (3) Wrong selection of technical staff

Keywords

Project Delays, Project Cost Over-Run, Project Time Over-Run.

Introduction

Construction projects can be successful when perspectives such as the scope of work, targeted time, quality, management, the experience of the project, and construction budget are taken into consideration. This study will mainly explore the causes of delays and cost overruns factors, in Construction Projects, as 9 out of 10 construction projects create delays and cost overruns. Cost overruns can be as much as 183 percent higher than the budgeted amount. Afghanistan needed a route to economic prosperity after decades of conflict, including modern highways, bridges, and power plants, as well as the capacity to sustain them. Construction projects are the major reason for the development of Afghanistan. Cost overruns and delays of a construction project in Afghanistan is a big problem facing construction Companies' workers and project employees with it. Generally, megaprojects experience delay and cost overruns.

Kamal khan dam was a big example of cost overruns and delay construction projects in Afghanistan. Kamal Khan is a hydroelectric project and irrigation dam on the Helmand River in the Chahar Burjak area of Nimroz province in Afghanistan. It was planned to be built in 1974 but due to the above-mentioned perspectives, the project was suspended. Afghanistan’s government has been working for the last 10 years to rebuild the dam. It was rebuilt in three phases, the first and second phases of the dam were surveyed, designed, and land acquisition, which began in 2012 to 2015 with an 80 million dollar budget. Once again, it was delayed due to a lack of budget. The last and third phase of construction of the dam began in 2017, four years, after which finally, in 2021 it got completed. The Afghan National Water Authority (NWARA) claims that the dam will irrigate about 1,75,000 hectares (432,434 hectares) of agricultural land. In addition, its reservoir has the capacity to store about 52 million cubic meters of freshwater. The overall cost of construction of the Kamal Khan dam is more than 111 million dollars. Besides governmental consumption on development projects, in capital and some provinces, people need houses. in 2014-15, 729 building was constructed valued USD169.6 million, and 523 buildings were on the phase of construction and the construction industry presents 7 to 10% of Gross Domestic Product (GDP) in the latest years stated by Ministry of Commerce and Industries. On the other hand, the Government of Afghanistan is not succeeded in building huge projects, for example, Sharake Jadid construction projects which will provide residency for three million persons. Master plan of this project was prepared with help of French, German and Afghan engineers which cast $60 million in 2008 and every unit of residency will cast 1000 thousand dollars, about 10 Ministry and governmental organization made association named Adara Mostaqa Kabul Jadid, this administration is responsible to work on this projects but there is no sign of any development of this project Figure 1.

Figure 1: Ranking Of Top 10 Factors Causes Of Delay.

Project Type: Types of projects are very important, most likely public project aspects delays and cost overrun more than private projects.

Project Location: Location of the project has an initial role in the successful completion of a project, like in this study location is Afghanistan because it is a country which has been at war for more than four decades, that caused the demolition of the entire infrastructure of this country, The construction industries play a major and crucial role in the economy's growth in Afghanistan. Also, the construction industry is the most important foundation of economic development, accounting for roughly 10% of the whole country's GDP. The building industry does have the great potential to underwrite to economic and societal development, but somehow it experiences several difficulties, including a lack of competitiveness, delays, and exorbitant prices, as well as consumer dissatisfaction issues, which have a straight impact on the economic development of the country and major investment level Figure 2.

Figure 2: Minimizing Method Of Project Delay.

Throughout the construction sector, be direct and foreign. Even though there have been many construction projects in Afghanistan in the past four decades, the economy is still feeble in the country due to decades of war and there is still the need for foreign funds and investments.

Literature Review

Karimi et al. (2020) found that the extreme level of bureaucracy has been one of the most puzzling issues in an infrastructure subdivision in many countries. Nations are diverse in many ways, such as institutional situations, organizational principles, and administrative equilibrium, and thus, Afghanistan's substructure division is no omission. Hence, this singularity has adversely obstructed the conveyance of infrastructure plans and hampered the nation in achieving its tactical monetary goal line. The result of this study will assist the administration to take required actions for abolishing redundant paces in the procurement civic structure schemes and eventually recovering project conveyance (Karimi et al., 2020).

Heravi &Mohammadian (2021) investigated 72 urban construction projects and analyzed delays and cost in urban construction projects in Iran. The size of the project, the nature of the project, the discrepancy amid low discounts and government assessments, and the intensity of concentration were found to be among the potential factors for the cost increase in the collected research. The main findings of the survey are: 1) Only 7% of the projects evaluated were finished on schedule and within budget, 2) About 8.5 percent of the projects under consideration were finished on schedule, 3) Costs and delays have increased for large urban construction ventures the instrument has been altered in every way. Superior to the restoration, urban road schemes have outperformed building projects in terms of cost-efficiency. Construction and rehabilitation project delays were not substantially different, and new road construction and maintenance project costs were not significantly higher (Hosaini & Singla, 2019).

(Alsuliman, 2019) studied reasons of delay in Saudi public construction projects. Data collected via questionnaire from 211 respondents; where 112 factors were distinguished that occur in all phases. These factors were divided into four main classes as (1) before tender award (2) during award (3) after award (4) general. Factors included in the first class are; no clear vision from the government side in the projects, lack of accuracy in site investigation, lack of coordination among ministries and companies, lack of accuracy in specification and drawings, lack of experienced and skilled Engineers Figure 3. The second class includes factors as; insufficient study of the site and tender form, award to the lowest bidder, insufficient analysis of competitor, an award of the project to contractors with low financial and technical potential, tenders are limited to specific contractors, tenders investigating committee are fixed and does not change. Third class includes factors as; delay in delivery of site, dispute on the site of project, government insufficient and inexperienced technical staff for overseeing, lack of project management administration, insufficient coordination among service provider involved in project, non-qualified consultant, lateness of the contractors in submitting the sales and requesting the supplies, weakness and no financial ability of contractors. The fourth class includes factors as; inexpert engineers for supervision, poor salaries and incentives for Engineers, corruption in estimating quantities, and prices (Alsuliman, 2019).

Figure 3: Ranking Of Top 10 Causes Of Cost Overruns Factors Over All View Of Respondents.

Callegari et al. (2018) conducted research on cost overrun and delays of megaprojects in Brazil. The massage deduced from this study is that; bigger projects include unmanageable risks that cannot be predicted and mitigated efficiently. the Result shows that the average cost of construction project rise 97.5 % above the initial estimated cost. the construction project experienced an average time escalation of 74.28% (Callegari et al., 2018)

Reshma identified that period and cost overruns in the UAE building sector have become a critical threat in the global construction sector. This paper investigated critical factors are: 1) the design varies from the client, 2) insubstantial scheduling, 3) schedules that are unreasonable, 4) timelines for completion, 5) delay in obtaining government permits, 6) Consultants' wrong method of time estimates, 7) Incorrect cost estimate, 8) The client's client decision-making process, and 9) Improper process of procurement (Callegari et al., 2018).

Raj Kapur Shah, investigated the causes of delays in Australia. He found that major cause by conducting three case studies on different parts to outline a relative analysis of construction delays and to categorize the variables into various importance levels of impact on project delays from state to state. According to the findings of these three case studies, the maximum important forces in Australia are: 1) Preparation and timing flaws, 2) Design processes, 3) Efficient supervision and consultation mechanism, 4) Payment certificate delays, 5) the most influential factors that are underestimating project costs, project difficulty, and project duration (Johnson et al., 2020).

Senouci, Ismail and Eldin explored while delay and cost overrun in Qatari public construction projects, therefore the researcher scanned extensively review of international and regional publication to distinguish fairly the problem and data was gathered from 122 public construction projects. ANOVA and regression analysis were done in this work to identify the relationship of cost overrun with the contract price. Consequently, cost overrun for building projects escalated with agreement charges but cost overrun for drainage projects diminished with an escalation of agreement prices (Niazi & Painting, 2017).

Msafiri investigated and analyzed the factors of construction time overruns in Kenya and discover that the key reasons for delays are: 1) Customer payment, 2) Poor decision-making, 3) Corruption in the customer organization, 4) Claims, 5) Insufficient schedule preparation, 6) Rain, 7)Site conditions (Shah, 2016).

Sweis (2013) examined that many construction projects in various developing countries are written off as overruns in time. The data are collected in two types. The overrun variables were taken out from the literature and from a detailed inspection of the observation of 30 engineers and then graded permitting their Severity Index (the product of Rank Index and Occurrence Index) (Frimpong et al., 2003). After directing the investigation on both the data, outcomes revealed that only one factor is responsible i.e., weather conditions. The outcome indicated that the major 10 elements significantly affecting construction efficiency in Afghanistan are; Security (Crime, fraud, and disorder), Payment delays, fraud, and a lack of drawings and measurements are all issues that need to be addressed. Poor planning and communication, as well as changes made during implementation deliveries to the construction phase, health and welfare on the job site (accidents), Raw materials of poor quality, and the shortage of materials (Sweis, 2013).

Aziz conducted research on delay factors in construction projects. This work main object was to distinguish and rank factors that initiated the delay in Egyptian construction projects on respect of relative importance. Construction project practitioners, experts were invited to participate in forming of questioner about 99 factors were listed as part of the questionnaire study in 9 categories. The questionnaire was responded by experts from the public and private construction companies Enshassi et al. (2009). For data analysis, the Relative Impotence Index was used. Factors were ranked according to their prominence and twenty most critical and twenty least critical were tabulated in this work five factors from twenty top are payment delay during project progress, bribes, insufficient planning, equipment shortage, poor site management. Five factors from the least critical are labor wounds in a site, no on-time site clearance, theft on-site, the clash among labors, wasting of time by circulation control at a job site (Sweis, 2013).

Kaliba et al. (2009) tudied delays and cost increases in road projects of Zambia. Data was collected with the help of a questionnaire, interview, case study from respondents and projects, where collected data was analyzed using Weight Opinion Average Figure 4.

Figure 4:Minimizing Method Of Cost Over-Runs.

Where WA is weighted average, Ri is the type of response in the Likert scale, rang from 1 to 4 and Fi is the frequency of respondents. The main factors of delay in road construction projects were procurement of construction materials, project drawing change, poor coordination between parties, disputes and difficulties between contractors and clients, staffing problems in the project, poor overseeing of projects work on-site and changes in specification. For cost escalation, main causes were; changes in project scope, protection and mitigating cost of environment, technical challenges, inflation and government pressure, bad weather or climate condition (Sweis, 2013).

A Comprehensive Review of the Literature Forty-Nine Factors’ Reasons for Cost Over-Runs

These variables are shown in seven groups. As presented in Table 1.

Table 1
Identified General Factors Of Cost Over-Run
Item General Factors of project Cost overrun Relegate
1 Lack in decision making process by the client Client
2 Slow payment of completed work by owner Client
3 Inflation and Escalation of material price change in project by owner Client
4 Method of economics and payment Client
5 Lack of coordination and poor communication with other parties Client
6 Financial difficulties of owner Client
7 Unfinished design at the tender time Client
8 security challenge during the implementation of projects Client
9 Weak site supervision and management by contractor Contractor
10 Poor experience of Contractor Contractor
11 Financial difficulty faced by contractor Contractor
12 Poor financial control on site Contractor
13 Corruption during award of the contract Contractor
14 Mistakes during construction Contractor
15 Number of projects going at the same time Contractor
16 project location Contractor
17 security challenge during the implementation of projects Contractor
18 Ineffectual scheduling and planning of project by contractor Contractor
19 Lack of financial management and planning Contractor
20 Inappropriate construction method Contractor
21 Delay in performing inspection Consultant
22 Inaccurate time and cost estimate Consultant
23 Poor Quality assurance Consultant
24 Inadequate experience of technical consultant Consultant
25 Delay in progress payment by owner Consultant
26 Changes in scope of project Consultant
27 Inadequate monitoring and control Consultant
28 extension of time with cost claims Consultant
29 Lack of coordination between parties Consultant
30 Construction materials shortage in the market Material
31 slow delivery of Construction material to site Material
32 Non-availability of construction materials Material
33 High transportation cost of materials Material
34 High quality of work required Material
35 Breakdowns of construction equipment Equipment
36 Construction equipment Shortage Equipment
37 insufficient operator's skill of equipment Equipment
38 High maintenance cost of machinery Equipment
39 High transportation cost of equipment Equipment
40 Security challenge during the transportation of machinery Equipment
41 Wrong selection of technical staff Labour
42 Lack of labours at site Labour
43 High labour cost on-site Labour
44 Shortage of technical personnel Labour
45 Weak motivation Labour
46 Overtime issues Labour
47 Accidents during construction External
48 Effect of weather on construction activities External
49 Corruption External
50 Impact of cultural and social factors External

Methodology

To complete this study, the data gathering tool was a questionnaire. The questionnaire is further split into 5 different sections which are as follows:

Section A includes general information of respondents as concerns, professional background, Education Level, grade of Membership, construction working experience, type of organization (Kaming et al., 1997).

Section B contains the factors that subsidize to reasons of delay in construction projects in Afghanistan,

Section C determines the factors causal reasons of cost over-run in construction projects in Afghanistan.

Section D contains the Effectiveness of delay and cost over-run in the construction project.

Section E determines minimizing methods of the above causes.

The Methodology is based on the quantitative method which SPSS software is used in Data analysis and outcomes presented in tables. Moreover, for statistical analysis, cloud-based software was used, as well as excel sheets and SPSS. The comparative significant index (RII) method was primarily used, and the variables were evaluated based on data collected from RII, to determine the correct consequence and find important considerations which had 69 delay factors and 49 reasons of construction project cost overruns taken from the literature review. Factors interrogated in the study. The ordinal scale was used to calculate the data from the questionnaire. For this study, an ordinal scale was used. Conferring to the degree of contribution used, the Likert gauge of four ordinal scales from 1 to 4 is used: 1, low, 2 medium, 3 high, and 4 very high. These considerations were divided into several categories. All the indexes and factors are shown in Table 2.

Table 2
General Factors Of Project Delay
S.No General Factors of project Delay Relegate
1 Delays in payments by the Client Client
2 Delays in delivery of the site to the contractor Client
3 During construction, the client made some modifications and maintained discipline. Client
4 Delay in the process of approving and verifying the Project sample and drawing. Client
5 suspensions of work by the owner Client
6 The weak mechanism of financial control. Client
7 Owner’s lack of experience Client
8 Delay in starting the process of planning, with a low amount of budget Client
9 Poor project management practices Client
10 Long term between design and tendering time. Client
11 Inadequacy of cost assessments prepared by government departments. Client
12 Change in project scope by owner Client
13 Contradictions in the subcontractor program in the project contractor execution Client
14 Ineffective implementation methods by contractor. Contractor
15 Disruptions at the work of sub-contractors Contractor
16 Lowly prerequisite of the contractor’s technical staff Contractor
17 Financial problems by contractors Contractor
18 subcontractor failures during construction Contractor
19 Lack of construction experience of contractors. Contractor
20 Incomplete scheduling and planning by the contractor. Contractor
21 Poor Coordination among contractors and other parties. Contractor
22 Improper construction methods implement Contractor
23 lack of technical professional in the contractor society Contractor
24 Ineffective technical operate allocated to the project. Contractor
25 Incompetent vendors and suppliers Contractor
26 Wrong method of cost estimate Contractor
27 Contractor’s deprived site management and supervision skills Contractor
28 During the construction phase, the builder faces cash flow and financial issues. Contractor
29 Non-existence of contractors’ manpower skill, knowledge and training Contractor
30 Lack of obtainable skilled and non-skilled labour Contractor
31 Lack of professional’s management staff. Contractor
32 Poor relationship between management and labour Contractor
33 Deprived site management by contractors Consultant
34 Absence of satisfactory experience of consultants Consultant
35 Stay in swotting the design documents Consultant
36 Unfortunate check plan by consultants Consultant
37 Errors & disagreement in design specification. Consultant
38 lack of connectivity and communication amongst consultant and parties Consultant
39 unclear and inadequate detail in drawing Consultant
40 Disputes between Consultants other groups. Consultant
41 Late progress report of completed work. Consultant
52 Poor material handling on site Consultant
43 Low quality of materials Material
44 Modifications in materials type and specifications during construction. Material
45 Delays in the manufacture of specific building material Material
46 Late-night obtaining of materials Material
47 Late-night in assortment of finishing materials due to diversity in market Material
48 Poor satisfaction and efficiency of the equipment. Material
49 Deficiency of high-tech mechanical machinery. Equipment
50 Incorrect selection of Construction equipment. Equipment
51 Corruption Equipment
52 Warlord’s influence External
53 Impacts of cultural and social factors. External
54 Land acquisition External
55 Natural disasters External
56 Far-off labour permits External
57 Market increase External
58 Currency vicissitudes External
59 Unsuitable type of award and bidding. External
60 Errors and inconsistency major contract documents External
61 delay execution final inspection and certification External
62 delay in locating permit from municipality External
63 Extreme weather (very cold, very hot, rain…) External
64 Water flood during irrigation construction projects External
65 Weak govt's regulatory mechanism for construction industrial dispute settlement External
66 Insufficient qualifications of Workforce External
67 The poor efficiency level of labour Labour
68 Personal conflict between laborers and management team Labour
69 Overtime issues Labour

The RII will be evaluated by the following equation:

Where Wi comes for weighting given to every factor by defendants (reaching from 1 to 4) A is the maximum weight (4 in this situation) and N comes for the total number of plaintiffs.

Data Analysis and Discussion

In this research work a total number of 106 questionnaires were disseminated to construction professional participator. 101 responses out of 106 questionnaires were received which was 34 managers, 24 Engineers/Consultants, 10 owners/clients, and 23 contractors. 10 sets of receiving responses were half-finished and considered as unreliable data for analysis. As a consequence, 91 sets of responses were suitable for analysis as shown in Table 3.

Table 3
Summary Of Categorized Responses
S.No. Classifying value
1 No. of responses disseminated 106
2 No. of received responses 101
3 No. of responses was half-finished (unreliable) 10
4 No. of responds 91
5 Per centum of responses received 95.284
  (%)  
6 Per centum of valid responses for evaluation % 85.85

Characteristics of the Participator

The survey participants had professional experience in realizing various kinds of construction projects. The table 4 below shows the frequency, percentage, and cumulative percentages of each respondent related to general information containing age, gender, education, designation, years of experience, and type of projects, they had experienced table 5. Overall, the characteristics of the respondents indicate that they were both qualified and experienced to participate in the questionnaire table 6 (Halloum & Bajracharya, 2012).

Table 4
Demographic Of The Participator
Respondents Demographic
Age Frequency Percent   Cumulative%
20-25 8 8.79     8.79      
25-30 17 18.68     27.47      
30-35 22 24.18     51.65      
35-40 28 30.77     82.42      
40-50 14 15.38     97.8      
Above 50 2 2.2     100      
Gender
Male       85     93.41 93.41
Female       6     6.59 100
Education
Graduate       65     71.43 71.43
Post Graduate       26     28.57 100
Designation
Manager       34     37.36 37.36
Engineer / Consultant       24     26.37 63.73
Client / Owner       10     10.99 74.72
Contractor       23     25.27 100
Experience
1-5 years     22     24.18   24.18
6-10 years     18     19.78   43.96
11-15 years     37     40.66   84.62
More than 15 years     14     15.38   100
Kinds of Projects Experienced
Academic buildings       42     46.15 46.15
Industry buildings       7     7.69 53.84
Residential buildings       23     25.27 79.12
Warehouse/distribution buildings       19     20.88 100
Table 5
Ranking Of Top 10 Factors Causes Of Delays Client, Contractors, Consultants, Materials, Equipment, External And Point View Of Labour
Point of view of Client, Contractors, consultants, materials, equipment, external and labour Percentage of Respondents RII Rank
4 3 2 1
Lack of coordination and poor communication with other parties 25 32 25 9 0.701 10
Difficulties in financing project by contractor 31 34 19 7 0.745 3
Deprived communication and coordination by contractor with other parties 19 42 26 4 0.709 9
Shortage in high-quality management personnel 21 43 22 5 0.72 5
Poor material handling on site 22 37 29 3 0.714 7
Corruption 43 24 20 4 0.791 2
security challenge during the implementation of projects 45 29 16 1 0.824 1
Warlord’s influence 21 40 27 3 0.717 6
Wrong selection 32 31 19 9 0.736 4
Shortage of technical staff 25 34 25 7 0.712 8
Table 6
Minimizing Method Of Project Delay
Minimizing Method of project delay Percentage of Respondents  RII Rank
  4 3 2 1
Clear objectives and scopes of work 36 31 17 7 0.764 1
Clear information/communication channel 36 22 28 5 0.745 4
Availability of resources 37 24 23 7 0.75 3
Top management support 38 25 23 5 0.764 1
Awarding bids to the right designer/ contractors 33 27 21 10 0.728 5
Use proper and modern construction equipment 25 34 25 7 0.712 6
Use of appropriate construction methods 14 45 25 7 0.681 7
Proper site management and supervision 22 33 24 12 0.679 8
Compressing construction duration 14 37 28 12 0.646 9

4.2. Ranking of Top 10 Factors causes of delays Client, Contractors, consultants, materials table 7, equipment, external and labor Point of View shown in table 8, table 9, table 10, table 11.

Table 7
Ranking Of Top 10 Causes Of Cost Overruns Factors Over All View Of Respondents
Over All Cost Overrun Factors Percentage of Respondents       RII Rank
  4 3 2 1
Slow payment of completed work by owner 27 35 20 9 0.7 5
 Poor site management and supervision 34 34 17 6 0.8 1
Financial difficulty faced by contractor 30 34 22 5 0.7 4
Security challenge during the implementation of projects 24 36 22 9 0.7 9
Delay in material delivery 27 29 28 7 0.7 7
Security challenge during the transportation of machinery 27 29 29 6 0.7 6
Accidents during construction 36 31 16 8 0.8 2
 Wrong selection 34 32 19 6 0.8 3
Shortage of site workers 25 30 32 4 0.7 7
Table 8
Minimizing Method Of Cost Over-Runs
Minimizing Method of cost over-runs Percentage Respondents  RII Rank
4 3 2 1
Appropriate planning and scheduling through the construction project 35 33 17 6 0.766 1
Impactful management to keep records of each task as well as its delivery time. 25 37 24 5 0.725 7
Before & after estimation and before purchase, material prices must be checked on a regular basis. 24 41 22 4 0.734 4
Observe the entire project overview employing effective methodology. 26 36 24 5 0.728 6
Ensure timely payment of employees and contractors, as well as site health and safety 28 37 21 5 0.742 2
Maintaining the project is important, but supporting the staff is essential to the project's achievement 26 36 25 4 0.731 5
The climate must be checked and tracked in advance. 18 41 26 6 0.695 8
Conferences with suppliers and contractors on a daily basis. 28 34 25 4 0.736 3
Table 9
Client Related Factors
Client related factors Percentage Respondents RII Rank
4 3 2 1    
Lack of coordination and poor communication with other parties 25 32 25 9  0.701 1
Poor financial control mechanism 26 27 28 10 0.690 2
Owner’s lack of experience 17 34 33 7 0.668 3
long term between design and tendering time. 13 40 28 10  0.654 5
several changes in owners’ necessities or characterisations 14 37 35 5 0.665 4
Table 10
Consultants Related Factors
Consultants Related Factors 4 3 2 1 RII  Rank
delay in approaching key vagaries in the scope of work 23 28 27 13 0.668 3
Poor site management by contractors 29 27 30 5 0.720 1
lack of coordination & communication 23 29 30 9 0.681 2
Non-existence of sufficient skill of consultants 14 36 28 13 0.640 4
Postponement in studying the design documents 11 38 30 12 0.632 5
Table 11
Contractors Related Factors
Contractors Related Factors 4 3 2 1 RII Rank
Financial difficulties by contractors 31 34 19 7 0.745 1
Poor Coordination among contractors and other parties. 19 42 26 4 0.709 3
Deprived requirement of the contractor’s technical staff 18 40 29 4 0.698 4
Inept technical staff assigned to the project 15 46 25 5 0.695 5
lack of technical professional in the contractor organization 21 43 22 5 0.720 2

Conclusions

In this Research the main goal is to find the main challenges and factors causing project delay and cost over-runs of construction projects in Afghanistan. Based on the results found from respondents’ through questioner, top 10 factors of cost overruns and project delay were analyzed and highest factor causing cost overruns and project delay is noted also the suitable solution found by minimizing method is suggested as below:

The highest factor causing cost overruns by related important index method ranked by all four groups of respondents such as clients, contractors, consultants and managers. The most important reasons of cost overrun are the following.

1. Unsuccessful Site Management and Administration: with an RII value of 0.764. On both large and small construction projects, supervision is essential to avoid incidents, planning and providing tasks, making decisions, monitoring productivity and implementation, establishing leadership and coordination, and maintaining employee involvement. As a consequence, supervision plays a significant role in the success of a typical construction project, especially in terms of maintaining that health and safety are effectively handled. The level of supervision required can be determined by the client's project management arrangements as well as risk evaluations conducted by contractors and others. But in Afghanistan most projects are cost overrun due to lack of supervision and site management. Construction leadership requires careful planning and scheduling. Engineers can complete a project on schedule and on budget by planning and coordinating construction tasks. The term "construction" encompasses not only bodily tasks counting workers, equipment, and machinery, but also the entire variety of activities involved in a construction project from conception to completion. Outcome, careful grounding and scheduling of each task are obligatory when handling resources such as men, materials, and machinery. Meanwhile, the best solution suggested for it by minimizing factor method is proper planning and scheduling throughout the construction project.

2. Security Challenges During the Implementation of Projects: All four groups of respondents have ranked with an RII value of 0.824 among top 10 factors, by related importance method that is the main cause of construction projects delay in Afghanistan. The Factor of security challenge during the implementation of construction project has the highest rank found by responses in Afghanistan. Since, due to insecurities in a large portion of the suburbs, the project’s implementation would be affected in several cases, such as: not being able to constantly supervise the project, delay infant and material delivery, skilled workers and engineers not willing to go for the job there, and even in serious cases the project might start without completion. On the other hand, this challenge can be decreased or even removed by undertaken some initial and specific precautions such us, clear objectives which government and stakeholders should consider a security preparation before planning the project and should allocate adequate funds and security guards for the project. From the very beginning of the project each and every task should be planned carefully with considering the project local condition, in addition, social coordinators should discuss the project goals and merits with local people and authorities in charge to prevent misunderstanding and smoothen execution of the project, also to ensure that further problems will not occur during the construction phase.

References

Alsuliman, J.A. (2019). Causes of delay in Saudi public construction projects.Alexandria Engineering Journal,58(2), 801-808.

Indexed at, Google Scholar, Cross Ref

Callegari, C., Szklo, A., & Schaeffer, R. (2018). Cost overruns and delays in energy megaprojects: How big is big enough?.Energy policy,114, 211-220.

Indexed at, Google Scholar, Cross Ref

Enshassi, A., Al-Najjar, J., & Kumaraswamy, M. (2009). Delays and cost overruns in the construction projects in the Gaza Strip.Journal of Financial Management of property and Construction,14(2), 126-151.

Indexed at, Google Scholar, Cross Ref

Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study.International Journal of project management,21(5), 321-326.

Halloum, M., & Bajracharya, A. (2012). Cost and time overrun revisited: a study on the infrastructure construction projects in abu dhabi, uae. InThird International Conference on Construction in Developing Countries, 4-6.

Google Scholar

Heravi, G., & Mohammadian, M. (2021). Investigating cost overruns and delay in urban construction projects in Iran.International Journal of Construction Management,21(9), 958-968.

Indexed at, Google Scholar, Cross Ref

Hosaini, S.B., & Singla, S. (2019). Significant factors of delay in construction projects in Afghanistan.International Journal of Innovative Technology and Exploring Engineering,8(95), 1060-1069.

Indexed at, Google Scholar, Cross Ref

Johnson, R.M., & Babu, R.I.I. (2020). Time and cost overruns in the UAE construction industry: a critical analysis.International Journal of Construction Management,20(5), 402-411.

Karimi, S., Zhakfar, Z., & Sarwary, M. I. (2020). Study of excessive bureaucracy in construction projects–causes of low level of competition and lengthy tendering process: a case study of afghanistan.International Journal of Engineering and Advanced Technology,10, 66-73.

Indexed at, Google Scholar, Cross Ref

Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing construction time and cost overruns on high-rise projects in Indonesia.Construction Management & Economics,15(1), 83-94.

Indexed at, Google Scholar, Cross Ref

Kaliba, C., Muya, M., & Mumba, K. (2009). Cost escalation and schedule delays in road construction projects in Zambia.International journal of project management,27(5), 522-531.

Niazi, G.A., & Painting, N. (2017). Significant factors causing cost overruns in the construction industry in Afghanistan.Procedia Engineering,182, 510-517.

Indexed at, Google Scholar, Cross Ref

Shah, R.K. (2016). An exploration of causes for delay and cost overrun in construction projects: A case study of Australia, Malaysia & Ghana.Journal of Advanced College of Engineering and Management,2(1), 41-55.

Google Scholar

Sweis, G.J. (2013). Factors affecting time overruns in public construction projects: The case of Jordan.International journal of business and management,8(23), 120.